Progress

Millestones

Name of the milestone
Associated action
Deadline
Executed
M E1.1 Project kick-off
E1
07/2017
OK
M A1.1 Bioactive peptides applications identification
A1
08/2017
OK
M A1.2 Successful definition of analytical methods and required equipment
A1
08/2017
OK
M A1.3 Successful installation of the brewing facilities
A1
08/2017
OK
M D1.1 Website Launch
D1
08/2017
OK
M D1.2 Dissemination and Communication plan
D1
12/2017
OK
M B1.1 Successful adaptation and optimization of the process: production of different product strams with favourable nutrients properties
B1
03/2018
OK
M B2.1 Successful demo-scale production of CYE and YCW with favourable nutrient properties
B2
01/2019
OK
M E1.2 Mid term report
E1
01/2019
OK
M B4.1 Successful substitution of the commercial yeast extract by the CYE in industrial fermentations in the pharma industry
B4
06/2019
OK
M C4.1 Animal feed study performed
C4
11/2019
M B3.1 Successful production of the beer with the CYE and YCW and successful sensory analysis
B3
12/2019
OK
M B3.2 Replacement of high protein malt by normal malt + CYE without affecting organoleptic characteristics
B3
12/2019
OK
M C1.1 LCA report
C1
12/2019
OK
M C2.1 Socio-economic and market report
C2
12/2019
OK
M C3.1 Technical plan for roll-out
C3
12/2019
OK
M C3.2 Fine-tuned business plan
C3
12/2019
OK
M C4.2 Contact with animal feed companies
C4
12/2019
OK
M C4.3 Contact with companies from fermentation industry
C4
12/2019
OK
M C4.4 Contact with food companies
C4
12/2019
OK
M C4.5 Contact with wine companies
C4
12/2019
OK
M C4.6 Contact with cosmetic industry
C4
12/2019
OK
M E1.3 Final report
E1
12/2019
OK
M E2.1 At least 4 other EU funded projects contacted
E2
12/2019
OK
M E4.1 After-LIFE plan finalized
E4
12/2019
OK
M E3.1 Final report with project indicators
E3
12/2019
OK

Follow-up meetings

Name of the milestone
Deadline
Executed
Kick-off meeting
07/2017
OK
Follow-up meeting 1- Partners
12/2017
OK
Follow-up meeting 2- Partners
04/2018
OK
Annual meeting 1- NEEMO
05/2018
OK
Follow-up meeting 2- Partners
01/2019
OK
Annual meeting 2- NEEMO
05/2019
OK
Industrial validation meeting
06/2019
OK
Final meeting
12/2019
OK